Pure Water Monterey Construction Updates

Phase II Injection Well Facilities Project

Haga clic para ver el PDF

Where

Fort Ord near General Jim Moore Blvd, San Pablo Ave, and Coe/Eucalyptus (see construction map below)

When

May 2018 – Est. March 2019
Monday – Friday 8:00 a.m. – 5:00p.m. (excluding holidays)
Some elements of construction will require 24-hour drilling operations 7 days a week. This stage is expected to begin this summer with mitigation measures being implemented, including the installation of approximately 100 feet of soundwall. Door tags will be distributed to alert residents before 24-hour activities begin.

What will you see?

  • Land clearing
  • Soundwalls
  • Construction machinery and personnel on the former Fort Ord, including Eucalyptus Rd
  • Tall drilling equipment

Potential Impact

  • Periods of drilling and general construction noise
  • Intermittent lane closures and traffic control from 9:00 a.m. – 3:00 p.m. on Gen. Jim Moore Blvd
    Residents will be able to access their homes at all times.

Current Construction Activity

June 2018

  • Site Grading
  • Percolation Basin Work
  • PG&E Primary Trenching
  • Monitoring Wells: Soundwall Installation and Rotary Drilling

 

Expanded construction details through June 22 here.

Project Contact

831-531-7545

purewatermonterey.org

PWM Construction Map

For information on the Pure Water Monterey Groundwater Replenishment Project, please visit PWM website.

For information on the Marina Coast Water District portion of the project, please visit the Regional Urban Water Augmentation Project website.

Actualizaciones de construccin en espaol

Actualizaciones de construccin en espaol (PDF)

Haga clic para ver el PDF

Construction Activity Timelines