Project Opportunities

RFPs/RFQs are shown below. RFP selection is based on qualifications.

Unless otherwise indicated, pre-proposal meetings are held at the Regional Treatment Plant (14811 Del Monte Boulevard, Marina). Contact project manager for directions or project information.

Pre-Proposal Meeting: N/A
Proposal Due Date:
Project Manager: , ,
Project Details (PDF): N/A
Project Documents (offsite): N/A

Unless otherwise indicated, pre-bid meetings are held at the Regional Treatment Plant (14811 Del Monte Boulevard, Marina).

Bids are publically open via the electronic bid management systems. Bidders may attend the opening at M1W Administrative Office, 5 Harris Court, Bldg. D, Monterey, CA 93940. Please contact the project manager for directions if needed.

Contact the identified Project Manager for specific project information.

Pure Water Monterey SCADA Integration - Ancillary SCADA Software and Hardware
Pre-Bid Meeting: N/A
Bid Due Date: Wednesday, May 29, 2019, 2:30 PM
Project Manager: Yohana Vargas, yohana@my1water.org, 831-883-6182
Project Details (PDF): N/A
Project Documents (offsite): View or Download
Monterey One Water is inviting bids for the supply and delivery of ancillary SCADA software and hardware for the project known as the Pure Water Monterey Project. 
Salinas Storm Water Grant (Phase 1B, Salinas Treatment Storage and Recovery Project)
Pre-Bid Meeting: Wednesday, April 17, 2019, 10:00 AM
Bid Due Date: Thursday, May 23, 2019, 2:30 PM
Project Manager: Alison Imamura, alison@my1water.org, 831-883-6176
Project Details (PDF): N/A
Project Documents (offsite): View or Download
The Project work covered by the Project includes construction of the facilities for the Salinas Storm Water Storage and Recovery Project at City of Salinas Industrial Wastewater Treatment Plant (IWTP) that will enable Monterey One Water (M1W) to divert treated and stored storm water to the M1W’s Regional Treatment Plant (RTP).
Salinas Storm Water Grant (Phase 1A, Dry Weather Diversion Project)
Pre-Bid Meeting: Wednesday, April 17, 2019, 10:00 AM
Bid Due Date: Monday, May 20, 2019, 2:30 PM
Project Manager: Alison Imamura, alison@my1water.org, 831-883-6176
Project Details (PDF): N/A
Project Documents (offsite): View or Download
Project work covered by the Project includes construction of the facilities for the Salinas Storm Water (Dry Weather Flow) Diversion for treatment and storage at City of Salinas Industrial Wastewater Treatment Plant (IWTP). Monterey One Water (M1W) will divert treated and stored storm water to the M1W’s Regional Treatment Plant (RTP) with facilities to be constructed under a separate project.

The Project will be funded by the State Water Resources Control Board Proposition 1 Storm Water Grant Program. Bids must comply with all requirements associated with these funding sources.
 

 
Lab Fume Hood Room Remodel
Pre-Bid Meeting: Tuesday, April 16, 2019, 10:00 AM
Bid Due Date: Friday, April 26, 2019, 2:00 PM
Project Manager: Jennifer Gonzalez, jennifer@my1water.org, 831-883-6172
Project Details (PDF): N/A
Project Documents (offsite): View or Download
SUMMARY OF WORK:
  1. Demo existing cabinetry and fume hoods.
  2. Installation of new electrical, plumbing, fume hoods and laboratory ovens including ducting and fans.
Pump Station 13 Valve Replacement and Upgrades Project

This project includes mechanical and electrical upgrades to increase the pump station's reliability and to further protect the Monterey Bay National Marine Sanctuary. The project is currently being designed by V.W. Housen & Associates. Construction is expected to begin in April 2017.

For results, visit the Bid Results & Pending Contracts page.